Established 1982

BUILDING

RESTORATION

INC.

Exceed your expectations

2423 Ravine Road
Kalamazoo, MI   49004

Phone: (269) 345-0567

Fax: (269) 345-9357

Home
Bronze Restoration
Building Cleaning
Carbon Graphite
Caulking/Sealing
Concrete Restoration
Containment
Elastomeric
Elevator
Epoxy Floors
Exterior Envelope
Flooring
Historic Preservation
Industrial Floor
Masonry
Pressure Grouting
Residential
Roofing
Structural Repair
Waterproofing
Water Intrusion
Employees

 

 

 

 

 

 

 

STRUCTURAL CONCRETE RESTORATION

After support shoring is installed, deteriorated concrete is removed to expose corroded structural steel.

Problem:  Severe corrosion and loss of load-bearing capacity of the structural support columns, girders and beams, and floor.

Constraints:  Facility in continuous operation.

Solution:  Remove and replace or supplement all deteriorated sections of structural concrete.

 



 

MICRO-SILICA CONCRETE OVERLAY

Problem:  Parking facility leaks on vehicles and stored materials.  Poor drainage of upper level.  Excessive corrosion of reinforcing steel in beams and columns.

Constraints:  50% of facility to remain in operation at all times.

Solution:  Repair all deteriorated concrete.  Supplement all defective reinforcing steel.  Install new drain system.  Install a 1 1/2" to 3" thick high density micro-silica concrete overlay.

 

 

CONCRETE TANK OVERLAY
A steel and fiber reinforced concrete base is being installed.

Problem:  Heavy deterioration of existing slabs and walls of a waste sludge tank.  Flat tank bottom not able to drain effectively.

Solution:  Install a 3/4" thick reinforced concrete wall liner at the lower 8 feet.  Install a sloped 2 foot thick reinforced concrete tank bottom.

 


 

EPOXY INJECTION

Low pressure injection ports are injected with epoxy resin.

Problem:  Prior to installation of a $250,000 printing press,  a cracked floor slab had to be repaired so as to avoid misalignment and vibration of the machine.

Constraints:  Facility in operation during repairs.

Solution:  Epoxy injection of slab to structurally adhere to floor slab together.

 

EPOXY INJECTION

Epoxy is injected into ports of deteriorating architectural facade system.

Problem:  Beautiful architectural art deco facade system is deteriorating from freeze/thaw problems.  Large pieces of facade are falling onto main entrance of sidewalk.

Constraints:  Main entrance will be in active use during repair procedures.

Solution:  Epoxy inject full depth of all cracks to regain structural integrity.  Recoat the entire facade to hide settlement from cracking and impregnate with a granite coating system to match original look.

 

  

STRUCTURAL ROTTED WOOD REPAIR

Eight inch steel channel section is bolted at 24" centers.

Problem:  Rotted wood beam supporting 20 feet of brick is supported by cast iron columns.

Constraints:  Removal of wood beam would cause the removal of 20 feet of 3 widths of brick.

Solution:  Epoxy consolidation of wood with 3 levels of epoxy consolidation.  Rebuild the most severely rottedwood.  Install 8" steel channel for residual strength. 

 

 

COLLAPSING BUILDING STRENGTHENING

Exterior and interior view of 1892 building.  600+ pieces of structural/scaffold shoring to re-jack building and provide temporary collapse prevention.

Problem:  High pressure steam leak in heating system for over 30 hours cause structural failure to framing system.

Constraints:  1892 construction structural system is now considered inadequate.

Solution:  Remove architectural elements within the interior.  Install new structural steel framing system within the building's interior, keeping the architectural elements of the original construction.  Repair all steam damage to walls, flooring, pews, ceilings, etc.

 

 

 

LARGE OPENING PROVIDED in LOAD BEARING WALL

Final adjustments are made to placement of 3,200 lb. beam in extremely confined workspace.

Problem:  Owner needs to expand paper mill machine though an existing wall area.  Wall is 26 inches thick, 32 feet high, 28 feet wide.

Constraint:  Two paper machines will be running during the entire operation.  Machines are located 6 inches away from the wall to be removed.  Temperature at ceiling is 110 degrees Fahrenheit with 100 percent humidity.  No debris is allowed to fall within the confines of the paper making process.

Solution:  Install a series of loading bearing peers, columns, beams and purlins outside of the wall area to permanently hold the roof and walls while removing the original load-bearing wall.

 

 

 

DETERIORATED CONCRETE REMOVAL EXPOSING CORRODING REINFORCING STEEL

Problem:  Chloride containing concrete caused corrosion of reinforcing steel at school building.

Constraints:  Because of high noise levels created during repair, building can only be worked on after school hours.

Solution:  Chip at night, shore, patch with 6000 PSI concrete.  Elastomeric coat finished surface.

 

 

 

Home ]     Visit our new product...Recycled Glass and Concrete Countertops.

Send mail to info@gobri.com with questions or comments about this web site.